§11755.1. Filing Schedule.
(a) Within sixty
(60) calendar days of receiving an application,
the Labor Commissioner shall inform the applicant
in writing that either:
(1) the application
is complete and accepted for filing, or
(2) the application
is incomplete, specifying the information required
to correct the deficiency.
(b) Within forty-five
(45) calendar days of accepting a complete application,
the Labor Commissioner shall inform the applicant
in writing of the decision on the application.
(c) The following
information is provided pursuant to Government
Code Section 15376. During the past two years,
the Division's time periods for processing an
application from the receipt of the initial application
to the final issuance or denial of certification
were as follows:
(1) The median time
was fifty (50) calendar days;
(2) The minimum
time was thirty (30) calendar days;
(3) The maximum
time was one hundred thirty-five (135) calendar
days.
NOTE: Authority
cited: Section 15376, Government Code. Reference:
Section 15376, Government Code.
HISTORY
- New section filed
3-4-86; effective thirtieth day thereafter (Register
86, No. 10).
- Renumbering of
former section 11755.1 to new section 11755.2
and new section 11755.1 filed 12-2-97; operative