23 CA ADC § 123


      23 CCR s 123

      Cal. Admin. Code tit. 23, s 123


      CALIFORNIA CODE OF REGULATIONS
      TITLE 23. WATERS
      DIVISION 1. RECLAMATION BOARD
      CHAPTER 1. ORGANIZATION, POWERS AND STANDARDS
      ARTICLE 8. STANDARDS
      This database is current through 05/19/06, Register 2006, No. 20.

      s 123. Pipelines, Conduits, and Utility Lines.

      (a) The following definitions apply to this section:

      (1) Delta Lowlands. "Delta Lowlands" means those lands within the 
      Sacramento-San Joaquin Delta that are approximately at the five- (5) foot 
      contour and below as shown in Figure 8.04.

      (2) Delta Uplands. "Delta Uplands" means those lands within the 
      Sacramento-San Joaquin Delta that are above the five- (5) foot contour as 
      shown in Figure 8.04.

      (b) Pipelines, conduits, utility lines, and appurtenant structures must 
      conform to the following criteria:

      (1) Pipelines, conduits, utility lines, utility poles, and appurtenant 
      structures may not be installed within the levee section, within ten (10) 
      feet of levee toes, or within the floodway during the flood season unless 
      authorized by the General Manager based on reservoir levels, stream 
      levels, and forecasted weather conditions on a case-by-case basis, 
      pursuant to section 11.

      (2) Appurtenant structures such as standpipes, utility poles, distribution 
      boxes, guy wires, and anchors, but not including siphon breakers, are 
      generally not permitted in or below the levee crown, on the levee slopes, 
      or within ten (10) feet of the levee toes. Appurtenant structures may be 
      permitted where they will not interfere with levee maintenance or flood 
      fight activities.

      (3) Appropriate, visible markers acceptable to the local maintaining 
      agency may be required to identify the location of buried pipelines, 
      conduits, and utility lines. A siphon breaker or other visible 
      appurtenance may be considered an acceptable marker for the attached 
      buried line. Markers must be made of durable, long lasting, fire-resistant 
      material, and must be maintained by the permittee until the pipeline, 
      conduit or utility line is properly abandoned.

      (4) Pipelines, conduits, and utility lines that pose a threat or danger to 
      levee maintenance or flood fight activities, such as high-voltage lines, 
      gas lines, and high pressure fluid lines, must be distinctively labeled to 
      identify the contents.

      (5) Buried high-voltage lines of greater than twenty-four (24) volts are 
      required to be protected with schedule 40 PVC conduit, or equivalent.

      (6) Overhead electrical and communication lines must have a minimum 
      vertical clearance above the levee crown and access ramps of twenty-one 
      (21) feet for lines carrying 750 volts or less, and twenty-five (25) feet 
      for lines carrying higher voltage.

      (7) Fluid- or gas-carrying pipelines installed parallel to a levee must be 
      a minimum distance of ten (10) feet from the levee toe and, where 
      practical, may not encroach into the projected levee slope.

      (8) Low-voltage electrical or communication lines of twenty-four (24) 
      volts or less may be installed parallel to a levee and within ten (10) 
      feet of the levee toe when it is demonstrated to be necessary and to not 
      interfere with the integrity of levee, levee maintenance, inspection, or 
      flood fight procedures.

      (9) The board may require the applicant to have any pipelines, conduits, 
      utility lines and appurtenant structures designed by a registered civil 
      engineer.

      (c) Pipelines, conduits, and utility lines installed within the floodway 
      must conform to the following additional conditions:

      (1) Pipelines, conduits, and utility lines installed within the floodway 
      must have a minimum cover of five (5) feet beneath the low-water channel, 
      and a minimum of two (2) feet in the remaining area of the floodway. A 
      greater depth of cover may be required based upon the feasibility of 
      achieving the required cover or local soil stability and channel 
      hydraulics.

      (2) Open-trench backfill to cover pipes must be placed in a manner 
      consistent with floodway characteristics such as erosion, deposition, and 
      streamflow velocities. This requirement is generally ensured by using 
      suitable material and compacting to the density of adjacent undisturbed 
      material. Compaction tests by a certified soils laboratory may be 
required.

      (3) In general, any standard material may be used for pipelines or 
      conduits to be installed within the floodway ten (10) feet or more from 
      the levee toe or the projected levee slope.

      (4) All debris that accumulates around utility poles and guy wires within 
      the floodway must be completely removed following the flood season and 
      immediately after major accumulations.

      (5) Pipelines and conduits which are open to the waterway and which could 
      cause flood damage from uncontrolled backflow during the design flood 
      event shall have a readily accessible positive closure device. A flap gate 
      is not a positive closure device.

      (d) Pipelines, conduits, and utility lines installed through a levee must 
      conform to the following additional conditions:

      (1) The installation of a fluid- or gas- carrying pipeline in a levee 
      section or within ten (10) feet of the toe parallel to the centerline is 
      not permitted.

      (2) Pipelines, conduits, and utility lines must be installed through a 
      levee as nearly at a right angle to the levee centerline as practical.

      (3) Buried pipelines, conduits, and utility lines that do not surface near 
      the levee toes must have location markers near both levee toes.

      (4) Buried pipelines, conduits, and utility lines that cross the levee at 
      right angles must have a location marker located on the levee slope 
      adjacent to either shoulder.

      (5) Buried pipelines, conduits, and utility lines that cross the levee at 
      other than right angles must have location markers on the levee slopes 
      adjacent to each shoulder.

      (6) Pipelines carrying gas or fluids under pressure must be confirmed free 
      of leaks during construction by pressure tests, X-ray, or equivalent 
      methods, and must be tested anytime after construction upon request of the 
      board.

      (7) Pipelines carrying gas or fluids under pressure must have a readily 
      accessible rapid closure device located within ten (10) feet of the 
      landside levee toe.

      (8) Pipelines and conduits open to the waterway must have a readily 
      accessible positive closure device unless it can be demonstrated it is not 
      necessary. A flap gate is not a positive closure device.

      (9) The side slopes of trenches excavated for the installation of 
      pipelines, conduit, or utility lines may be no steeper than one (1) foot 
      horizontal to one (1) foot vertical. The following are exceptions to this 
      maximum slope requirement:

      (A) For shallow installations above the flood plane, e.g., twelve (12) 
      inches, vertical side slopes may be allowed.

      (B) For that portion of the trench above the design freeboard, vertical 
      side slopes may be allowed.

      (10) The bottom width of trenches excavated for the installation of a 
      pipeline, conduit, or utility line must be two (2) feet wider than the 
      diameter of the pipeline or conduit, or two (2) times the pipe diameter, 
      whichever is greater.

      (11) The minimum cover for pipelines, conduits, and utility lines 
      installed through the levee crown is twenty-four (24) inches. If it 
      becomes necessary to raise a levee crown to provide minimum cover, the 
      longitudinal slope of the crown must be a minimum of ten (10) feet 
      horizontal to one (1) foot vertical. Where twenty-four (24) inches of 
      cover is not practical, a concrete or other engineered cover is required.

      (12) The minimum cover for pipelines, conduits, and utility lines 
      installed within the levee slope is twelve (12) inches. Where the 
      installation will not interfere with levee maintenance or flood fight 
      activities, it may not be necessary to bury the line within the levee 
      slopes.

      (13) When practical, pipelines, conduits, and utility lines installed 
      within a levee section must be separated from parallel pipelines, 
      conduits, and utility lines by a minimum of twelve (12) inches, or the 
      diameter of the largest pipeline, conduit, or utility line, whichever is 
      larger, to a maximum of thirty-six (36) inches.

      (14) When practical, pipelines, conduits, and utility lines must have a 
      minimum vertical spacing of six (6) inches when crossing other pipelines, 
      conduits, or utility lines.

      (15) A siphon breaker with a protective housing may be required and must 
      be installed off the levee crown roadway where it will not interfere with 
      levee maintenance.

      (16) Electrical and communication lines installed through a levee or 
      within ten (10) feet of a levee toe must be encased in schedule 40 PVC 
      conduit or equivalent. Low-voltage lines (24 volts or less) and fiber 
      optic cable may be allowed without conduit if properly labeled.

      (17) A standard reinforced concrete U-wall for levee erosion protection is 
      required at the outlet end of a pipeline or conduit discharging within ten 
      (10) feet of a levee toe. See Figures 8.05 and 8.06 for U-Wall design 
      criteria.

      (18) Existing levee erosion protection must be restored by the permittee 
      if it is damaged during the installation of a pipeline, conduit, or 
      utility line.

      (19) The permittee must replant or reseed levee slopes to restore sod, 
      grasses or other nonwoody ground covers that are destroyed or damaged 
      during the installation of a pipeline, conduit, or utility line.

      (20) Within the levee or within ten (10) feet of levee toes, any 
      excavation for the installation of a pipeline, conduit, or utility line 
      must be backfilled in four (4) to six- (6) inch layers with approved 
      material and compacted to a relative compaction of not less than ninety 
      (90) percent, per ASTM D1557- 91, dated 1991, which is incorporated by 
      reference and above optimum moisture content or ninety-seven (97) percent, 
      per ASTM D698-91, dated 1991, which is incorporated by reference and at or 
      above optimum moisture content. Compaction tests by a certified soils 
      laboratory will be required to verify compaction of backfill within a 
      levee.

      (21) Boring a pipeline or conduit through a levee is permitted if the 
      following additional conditions are met:

      (A) The invert of the pipeline or conduit must be located at least three 
      (3) feet above the design flood plane.

      (B) The pipeline or conduit must be butt-welded. Polyethylene pipes may be 
      used as provided in subdivisions (f)(4)(A), (f)(4)(B), and (f)(4)(C) of 
      this section.

      (C) The pipeline or conduit must be installed by the bentonite boring 
      method or equivalent. The bentonite boring method uses an auger followed 
      by a pipe with multiple port openings through which a bentonite slurry is 
      pumped to ensure sealing of any voids resulting from the boring process.

      (e) Pipelines, conduits, and utility lines may be installed by the open 
      cut-method through a levee below the design flood plane, or within the 
      levee foundation under the following conditions:

      (1) One or more of the following conditions must apply:

      (A) The pipeline, conduit, or utility line will be maintained by a public 
      agency with a history of good maintenance based upon annual maintenance or 
      inspection reports.

      (B) The levee is designed to withstand a depth of less than six (6) feet 
      of water measured with respect to the elevation of the landside levee toe.

      (C) The levee is designed to withstand a depth of less than twelve (12) 
      feet of water measured with respect to the elevation of the landside levee 
      toe and provides flood protection for a rural area, or an area where the 
      board anticipates little future urban development.

      (2) Pipelines open to the waterway must be a minimum of thirty (30) inches 
      in diameter, and must have a readily accessible positive closure device 
      installed on the waterward side.

      (3) Seepage along pipelines, conduits, and utility lines must be prevented 
      by either of the following methods:

      (A) The pipeline, conduit, or utility line is encased in reinforced 
      concrete cast against firm undisturbed earth.

      (B) The conduit has reinforced concrete battered walls at an inclination 
      of one (1) foot horizontal to four (4) feet vertical or flatter.

      (4) The work must commence and be completed prior to the flood season.

      (5) Levees located within the Sacramento-San Joaquin Delta lowlands may 
      only be cut below the design flood plane after appropriate engineering 
      studies are performed and approved.

      (f) Pipelines, conduits, and utility lines may be installed under a levee 
      or stream channel by tunneling, jacking, or boring, if the following 
      conditions are met:

      (1) The pipeline, conduit, or utility line is at least thirty (30) feet 
      under the levee.

      (2) The pipeline, conduit, or utility line is verified to have the 
      required cover. A greater depth of cover may be required based upon the 
      feasibility of achieving the required cover or on local soil stability and 
      channel hydraulics.

      (3) If the installation is to be more than fifty (50) feet below the levee 
      and the entire floodway and streambed, the board may waive the requirement 
      for a permit provided a letter of intent is filed with the board prior to 
      commencement of the project.

      (4) The portal and outlet of a tunnel, jacking, or boring must be a 
      minimum distance of ten (10) feet beyond the projected levee slope without 
      an approved stability and seepage analysis.

      (5) Installation may occur during the flood season and when the water 
      surface elevation in the floodway is expected to be above the elevation of 
      the landside levee toe if adequate containment cells are constructed at 
      the portal and outlet.

      (6) The installation of a pipeline, conduit, or utility line under levees 
      in the Sacramento-San Joaquin Delta lowlands requires adequate containment 
      cells at the portal and outlet when the installation is less than fifty 
      (50) feet below the streambed and levee toes.

      (7) Pipelines carrying gas or fluids under pressure below a levee must 
      have provision for rapid closure.

      (8) Pipelines and conduits open to the waterway and below a levee must 
      have a positive closure device which is accessible at all times unless it 
      is demonstrated to be unnecessary. A flap gate is not a positive closure 
      device.

      (g) The following pipe materials are allowed within a levee section when 
      designed to resist all anticipated loading conditions and properly 
      installed:

      (1) Galvanized iron pipe is allowed if all joints are threaded. Galvanized 
      iron pipe joints must be corrosion protected with PVC tape or polyethylene 
      tape wrapped to a thickness of thirty (30) mils or equivalent.

      (2) Schedule 80 polyvinyl chloride (PVC) pipe is allowed if it is entirely 
      buried, all joints are threaded and the components were continually 
      protected from ultraviolet radiation damage or were newly manufactured.

      (3) Polyvinyl chloride (PVC) plastic pipe schedule 40, or better, may be 
      used as a conduit for power or communication cables.

      (4) High-density polyethylene pipe may be used for pipeline or conduit 
      installations provided the following conditions are met:

      (A) High-density polyethylene pipeline or conduit joints must be heat or 
      electrofusion welded (ASTM Standard F1055-93, dated 1993 or D3261-93, 
      dated 1993 which is incorporated by reference).

      (B) High-density polyethylene pipelines and conduits must be designed to 
      resist all anticipated loading conditions, and the design calculations 
      must be submitted to the board.

      (C) High-density polyethylene pipelines and conduits must be ultraviolet 
      radiation protected.

      (5) Cast-in-place reinforced concrete pipes and box culverts may be used 
      above and below the design flood plane if the concrete is at least six (6) 
      inches thick.

      (6) Precast reinforced concrete pipes and box culverts and concrete 
      cylinder pipes may be used above and below the design flood plane if the 
      following conditions are met:

      (A) Precast reinforced concrete pipe meets ASTM Specification C76-90, 
      dated 1990 which is incorporated by reference.

      (B) Precast reinforced concrete pipe joints and precast box culvert joints 
      are encased in reinforced concrete cast-in-place against firm undisturbed 
      earth.

      (C) The cylinders of concrete cylinder pipes are welded and corrosion 
      protected internally and externally.

      (D) When installed below the design flood plane, precast reinforced 
      concrete pipe and concrete cylinder pipe must be encased below the 
      springline in concrete cast against undisturbed earth.

      (7) Steel pipe may be used for all types of pipeline or conduit 
      installations through a levee above the design flood plane if the pipe 
      meets the following requirements:

      (A) The steel pipe is resilient and not materially reduced in quality due 
      to weathering, prior use or other deteriorating conditions.

      (B) The steel pipe joints are butt-welded or threaded.

      (C) The steel pipe installations are corrosion-proofed externally with a 
      coating of material such as coal-tar enamel, asphalt-dipped wrap, mortar, 
      PVC tape, or polyethylene tape wrapped to a thickness of thirty (30) mils, 
      high solids epoxy, or equivalent.

      (D) Unless a continuous internal lining of cement, mortar, or equivalent 
      is provided, as appropriate for the fluid to be conveyed, new steel pipe 
      installations may convey only non- corrosive material, and water is 
      considered corrosive.

      (E) Steel pipe installations must be designed to resist all anticipated 
      loading conditions, and the design calculations must be submitted to the 
      board. Steel pipe meeting the following criteria may be used without 
      submittal of design calculations to the board:

      (i) Twelve- (12) inches in diameter or less ten- (10) gauge steel pipe.

      (ii) Greater than twelve- (12) inches and a maximum of thirty- (30) inches 
      in diameter seven- (7) gauge steel pipe.

      (iii) Greater than thirty- (30) inches and a maximum of forty-eight (48) 
      inches in diameter three- (3) gauge steel pipe.

      (h) The following materials are not allowed for pipelines or conduits used 
      to carry natural gas or fluids:

      (1) Aluminum pipe within a levee section or within ten (10) feet of levee 
      toes.

      (2) Cast iron pipe within a levee section or within ten (10) feet of levee 
      toes.

      (3) Pipe with flanges, flexible couplings, or other mechanical couplings 
      within a levee section or within ten (10) feet of levee toes.

      (4) Prestressed concrete pipe within a levee section or within ten (10) 
      feet of levee toes.




      Image 1 (8.5" X 5.75") Not available for Offline Print to STP or FAX





      Image 2 (8.5" X 6.5") Not available for Offline Print to STP or FAX





      Image 3 (8.5" X 6.5") Not available for Offline Print to STP or FAX




      


      Note: Authority cited: Section 8571, Water Code. Reference: Sections 8608, 
      8710 and 8712, Water Code. 


       HISTORY 
         
      1. New section and figures 8.04, 8.05 and 8.06 filed 9-30-96; operative 
      10-30-
      96 (Register 96, No. 40).
      23 CA ADC s 123

      END OF DOCUMENT

      (C) Copyright 2006, Result Oriented Marketing, Inc.
      For Further Assistance Visit : www.mcmillanlaw.us and www.fearnotlaw.com   
 
Home | About Us | Contact Form | Contact Us | Useful Links


© Copyright 2006, Result Oriented Marketing, Inc.
For Further Assistance Visit : www.mcmillanlaw.us and www.fearnotlaw.com