23 CA ADC § 128
23 CCR s 128
Cal. Admin. Code tit. 23, s 128
CALIFORNIA CODE OF REGULATIONS
TITLE 23. WATERS
DIVISION 1. RECLAMATION BOARD
CHAPTER 1. ORGANIZATION, POWERS AND STANDARDS
ARTICLE 8. STANDARDS
This database is current through 05/19/06, Register 2006, No. 20.
s 128. Bridges.
(a) The standards for construction or modification of bridges within an
adopted plan of flood control are as follows:
(1) Any excavation within the levee section or near bridge supports within
the floodway must be backfilled in four- (4) inch to six- (6) inch layers
with approved material. The levee section must be compacted to a relative
compaction of not less than ninety (90) percent per ASTM D1557-91, dated
1991, which is incorporated by reference and above optimum moisture
content. Compaction within the floodway must be to the density of the
adjacent undisturbed material.
(2) Compaction tests by a certified soils laboratory may be required to
verify compaction.
(3) Bridge piers and bents within the floodway must be constructed
parallel to the direction of streamflow.
(4) Bridge piers and bents placed within a floodway to support a widened
portion of an existing bridge must be constructed in line with existing
bents and piers.
(5) Erosion control may be required on the channel banks or levee slopes
upstream and downstream of a proposed bridge.
(6) Drainage from a bridge or highway may not be discharged onto a levee
section or streambank.
(7) Plans showing all construction facilities (such as temporary staging,
coffer dams, and falsework) which will remain in a floodway during flood
season, must be submitted to the board for approval prior to installation
of these facilities.
(8) All construction facilities (such as temporary staging, coffer dams,
and falsework) must be designed to prevent bank erosion during normal
flows and to maintain maximum channel capacity during the flood season.
(9) Stockpiled material, temporary buildings, construction equipment, and
detours that obstruct streamflows must be removed from floodways prior to
the flood season.
(10)(A) The bottom members (soffit) of a proposed bridge must be at least
three (3) feet above the design flood plane. The required clearance may be
reduced to two (2) feet on minor streams at sites where significant
amounts of stream debris are unlikely.
(B) When an existing bridge being widened does not meet the clearance
requirement above the design flood plane, the bottom structural members of
the added section may be no lower than the bottom structural members of
the existing bridge, except as may be caused by the extension of existing
sloped structural members.
(C) When the clearance requirement above design flood plane would result
in bridge approach ramp fill in the floodway, the clearance requirement
may be reduced to the extent that reasonably balances clearance and fill
that would obstruct flow, so as to maintain maximum channel capacity.
(11)(A) Vehicular access from the roadway to the levee crown may be
required at each end of a bridge.
(B) Vehicular access from the levee crown to the floodway and/or the
landside levee toe beneath the bridge may be required. Ramps may slope
upstream as necessary to provide the access required by this subdivision.
(12) Approved gates must be installed at right angles across the levee
crown at all points of access to the levee from each end of a bridge.
(13) Any bridge abandoned or being dismantled must be completely removed,
and must be disposed of outside the limits of the levee section and
floodway.
(14) Pilings, piers, bents, and abutments of bridges being dismantled must
be removed to at least one (1) foot below the natural ground line and at
least three (3) feet below the bottom of the low water channel.
(15) Any bridge that is damaged to the extent that it may impair the
channel or floodway capacity must be repaired or removed prior to the next
flood season.
(16) Replacement railroad bridges must have the soffit members no lower
than those of the replaced bridge, but are not required to have a
specified amount of clearance above the design flood plane.
(17) Bridge replacements and new bridges shall be built at an elevation so
that there is no depression in the crown of the levee.
(b) The standards for maintenance of bridges within an adopted plan of
flood control are as follows:
(1) The area in and around a bridge site must be kept clear to maintain
the design flow capacity.
(2) Trees, brush, sediment, and other debris must be kept cleared from the
bridge site and be disposed of outside the limits of the floodway prior to
the flood season.
(3) Any accumulation of debris during high flows must be immediately
removed from a bridge site and disposed of outside the floodway.
Note: Authority cited: Section 8571, Water Code. Reference: Sections 8608,
8609 and 8710, Water Code.
HISTORY
1. New section filed 9-30-96; operative 10-30-96 (Register 96, No. 40).
23 CA ADC s 128
END OF DOCUMENT
(C) Copyright 2006, Result Oriented Marketing, Inc.
For Further Assistance Visit : www.mcmillanlaw.us and www.fearnotlaw.com
|