23 CA ADC § 130
23 CCR s 130
Cal. Admin. Code tit. 23, s 130
CALIFORNIA CODE OF REGULATIONS
TITLE 23. WATERS
DIVISION 1. RECLAMATION BOARD
CHAPTER 1. ORGANIZATION, POWERS AND STANDARDS
ARTICLE 8. STANDARDS
This database is current through 05/19/06, Register 2006, No. 20.
s 130. Patrol Roads and Access Ramps.
(a) The following definitions apply to this section:
(1) Access Ramps - "Access Ramps" mean those ramps that provide access to
the levee crown from adjacent property and roads.
(2) Patrol Roads - "Patrol Roads" means those roads that provide vehicular
access along levee crowns and flood channels for inspection, maintenance,
and flood fighting.
(b) Patrol roads must meet the following criteria:
(1) Patrol roads must be surfaced with a minimum of four (4) inches of
compacted, class 2 aggregate base (Caltrans Spec. 26-1.02A, July 1992)
which is incorporated by reference, or equivalent.
(2) Patrol road surfacing material must be compacted to a relative
compaction of not less than ninety (90) percent per ASTM D1557-91, dated
1991, which is incorporated by reference with moisture content sufficient
to obtain the required compaction.
(3) Compaction tests by a certified soils laboratory may be required to
verify compaction.
(4) Paved patrol roads must meet the design requirements for paved bicycle
trails, section 132.
(5) Levee crown surfacing must meet the following additional requirements:
(A) Where the crown width is less than sixteen (16) feet, the minimum
surfacing width must be ten (10) feet with a smoothly tapered transition
to the edge of the levee shoulder.
(B) Where the crown width is sixteen (16) feet or more, the minimum
surfacing width must be twelve (12) feet with a two (2) foot-wide taper at
each edge of the surfacing.
(C) The crown roadway must be sloped a minimum of two- (2) percent.
(6) Any patrol road which has been excavated or damaged must be restored
to its original condition.
(c) Access ramps are of two common types, head-on or side approach, and
must meet the following criteria:
(1) Access ramps must be constructed of approved imported material.
(2) The surfacing for all access ramps must be the same as for patrol
roads. Subdivisions (b)(1), (b)(2) and (b)(3) of this section also apply
to access ramps.
(3) Any excavation made in a levee section to key the ramp to the levee
must be backfilled in four- (4) to six- (6) inch layers with approved
material and compacted to a relative compaction of not less than ninety
(90) percent per ASTM D1557-91, dated 1991, and above optimum moisture
content.
(4) Compaction tests by a certified soils laboratory may be required to
verify compaction.
(5) All access ramps must be constructed in such a manner so as to direct
all surface drainage away from the levee section.
(6) Approved gates must be installed across access ramps at locations
where vehicular access by the public is possible.
(7) Side approach ramps must be used on the waterside levee slope.
(8) Side approach ramps on the waterward slope of the levee must slope
downstream.
(9) Typical plans for each type of approach ramp with restrictions and
requirements are shown on Figures 8.08 and 8.09.
Image 1 (8.5" X 6.5") Not available for Offline Print to STP or FAX
Image 2 (8.5" X 6.5") Not available for Offline Print to STP or FAX
Note: Authority cited: Section 8571, Water Code. Reference: Sections 8608
and 8710, Water Code.
HISTORY
1. New section and figures 8.08 and 8.09 filed 9-30-96; operative 10-30-96
(Register 96, No. 40).
23 CA ADC s 130
END OF DOCUMENT
(C) Copyright 2006, Result Oriented Marketing, Inc.
For Further Assistance Visit : www.mcmillanlaw.us and www.fearnotlaw.com
|