s 8. Applications.
(a) All applications for approval must be on forms provided by the board.
Applications to the board must be typewritten or in legible handwriting in
ink and signed by or on behalf of the applicant. Applicants must furnish
copies of other material as may be needed by the board and its staff to
adequately determine the exact nature of the proposed work and its effect
upon any project facilities or adopted plan of flood control. Applications
and all associated material must be filed in quadruplicate (4 copies) with
the office of the board. A copy of the application form is found in
Appendix A.
(b) Information furnished to the board must include:
(1) A description of the proposed work, together with a statement of the
dates the planned construction will be initiated and completed.
(2) A completed copy of the Environmental Assessment Questionnaire that
accompanies the application form from the board (See Appendix A) and a
copy of any draft and final environmental review document prepared for the
project, such as an initial study, environmental assessment, negative
declaration, notice of exemption, or environmental impact report. For any
reasonably foreseeable significant environmental impacts, mitigation for
such impacts shall be proposed.
(3) Complete plans and specifications showing the proposed work, including
a location map showing the site of the work with relation to topographic
features; a plan view of the area; and adequate cross sections through the
area of the proposed work. The plans must be drawn to scale and refer to
National Geodetic Vertical Datum (NGVD), or other known datum. The plans
must also indicate any project features such as levees and/or channels,
roads, or other structures, and must show river mile or levee mile
references. The dimensions of any proposed or existing fills, excavations,
and construction must be given.
(4) Additional information, such as geotechnical exploration, soil
testing, hydraulic or sediment transport studies, biological surveys,
environmental surveys and other analyses may be required at any time prior
to board action on the application.
(5) The names and addresses of all landowners adjacent to the property on
which the project is located.
(c) The Board may waive minor variations in an application.
Note: Authority cited: Section 8571, Water Code. Reference: Section 2090,
Fish and Game Code; Sections 21080.3, 21104.2 and 21160, Public Resources
Code; and Sections 8611, 8710 and 8730.3, Water Code.
HISTORY
1. Renumbering and amendment of old section 16 to new section 8 filed
9-30-96;
operative 10-30-96 (Register 96, No. 40). For prior history, see Register
85, No. 26.
23 CA ADC s 8
END OF DOCUMENT
(C) Copyright 2006, Result Oriented Marketing, Inc.
For Further Assistance Visit : www.mcmillanlaw.us and www.fearnotlaw.com
|